Subcontractor to supply and fix form work to concrete walls Supply and Erection of DOKA wall formwork to the shearwalls. The installation had to follow the DOKA frami support without the use of tie-rods in order to avoid radiation leakages from the rooms. The installation followed a robust panel support using a prop and walling system with anchorage and tie bolts to the over hangs of the vertical wailers. Major challenges of high concrete pressures and vertical uplift to the erect system due to the elimination of tie rods had to be resolved using ground anchors to the concrete slab.
Employer's Name:
ROKO